Totals in the material list
What the purchase, transit, warehouse, site and written-off totals show and how to read them.
The specification header shows totals broken down by section. It is the fastest way to understand the state of purchasing for a stage.
What the totals show
Purchase — how much is still to be spent. This is plan, not fact.
Delivery — how much money is tied up in goods bought but not received. The most worrying figure: these materials are paid for, but nobody has confirmed they exist.
Warehouse — what is in storage. Your stock, but not yet a cost against the object.
Site — what has actually gone into the work. This is the real material cost of the stage.
How to read it
Add Warehouse and Site together — that is what you definitely received. Compare it with Delivery: if Delivery is of a similar size, goods receipt is not being recorded properly.
Look at Purchase against the stage dates. A large amount still to buy a week before work starts means the materials will not be on site in time.
Plan against fact
Before purchase the totals use planned prices; afterwards, actual ones. So the figures shift during purchasing not only because items move but because real prices differ from the estimate.
The gap between your original estimate for a stage and its final total is the most useful number you will have for the next project.
Levels
Totals are calculated for a task, a stage and a project. The stage specification is assembled from its tasks automatically, so stage totals are always current without any manual reconciliation.
Next
Material movement: ordered, in transit, warehouse, site
Writing off materials
Material database and prices

